Toll Pejagan-East Brebes Completed, Jokowi: Eid It Can Be Used
Toll Project Pejagan-East Brebes eventually some already completed. The highway is targeted to be used when Lebaran this year.
"It was finished anyway, for Lebaran is (can be used). It has been 100% completed, finishing little bit," said President Joko Widodo (Jokowi) at Toll Gate East Brebes, Monday (04/11/2016).
Currently Section I and II Toll-Brebes Pejagan east along the 21 km has been completed. The rest, Section III and IV along 37 km will be completed next year.
Toll Pejagan-East Brebes |
Currently Section I and II Toll-Brebes Pejagan east along the 21 km has been completed. The rest, Section III and IV along 37 km will be completed next year.
"Then that is 37 km, God willing, I give the target one year earlier to PUPR Minister, Minister of State, Director of Waskita completed," said Jokowi.PT Waskita through its subsidiary, PT Waskita Toll Road, take over the concession of the toll road 14 months ago. After 20 years worked by the old company, this toll could eventually completed.
"The 37 km that the next year, but it can be said is not a problem," he said.